2792

For possible action. Discussion to approve and award a contract to Farr Construction Corporation d.b.a Resource Development Company or to KG Walters Construction Company, Inc., for the construction of the North Valley Wastewater Treatment Plant Improvements project. (Nicholas Charles)

Information

Department:Public WorksSponsors:
Category:Agreement

Attachments

  1. Printout
  2. 2018-01 NVWWTP Contracts Memo

Financial Impact

The North Valley WWTP project has identified funding through a State Revolving Fund (SRF) loan, Redevelopment Agency (RDA) funds, and a Community Development Block Grant (CDBG) totaling $10,392,939. The proposed construction contract exceeds available funding, creating a project budget deficit of $1,204,588 to $1,284,503 (depending upon the general contractor the project is awarded to). It is proposed that this deficit be covered through capital reserves. The available balance in capital reserves is $2,399,633 with total reserves in the Sewer Fund of $3,118,954.

DO NOT USE

<<DO NOT USE>>

Meeting History

Dec 21, 2017 1:30 PM Video Board of County Commissioners Regular Meeting
RESULT:CONTINUED [UNANIMOUS]Next: 1/4/2018 1:00 PM
AYES:Barry Penzel, Steve Thaler, Nancy McDermid, Larry Walsh, Dave Nelson
Jan 4, 2018 1:00 PM Video Board of County Commissioners Regular Meeting
RESULT:CONTINUED [UNANIMOUS]Next: 1/18/2018 1:30 PM
AYES:Barry Penzel, Steve Thaler, Nancy McDermid, Larry Walsh, Dave Nelson